EFFINGHAM, IL-(Effingham Radio)- The contractor, B&T Drainage has made good progress this week.
The new 10″ pipe is in place from Banker Street to Third Street and was connected to the existing water main at Third but will not be turned on yet.
There is still pipe to be placed on Jefferson between Banker and Front and on Banker, 5th, 4th, and 3rd.
Once all of the new pipes are placed, the new lines are filled from the connection at Third Street and disinfected, pressure tested, flushed, and then sampled.
When the samples have passed the required IEPA analysis, work can begin on switching water services to the new pipes.
It is estimated that the remaining work on installing the pipe will take 2 to 3 weeks if there are no weather interruptions.
B&T has informed the City that as of today, they do not plan on being onsite next week due to a forecast with snow and below zero temperatures.
The City will provide an updated work schedule next week.
The City of Effingham and B&T Drainage appreciates everyone’s patience and cooperation during the project.
If there are any questions or concerns, please contact Greg Koester of the City of Effingham by phone or text at (217) 821-7731 or email at gkoester@effinghamil.com.
UPDATE 7:43PM (01/21/19) – The contractor will be taking advantage of the warmer weather Tuesday, January 22nd and will be installing the new water main between Banker Street and Front Street.
This will require the closure of the westbound lane and the parking on the North Side of Jefferson Avenue.
In addition, Front Street and Banker Street between Jefferson Avenue and Washington Avenue will be closed.